# Carlyss Drive Extension Redesigned for Private School Access as Completion Moves Into 2027
- URL: https://www.thecalcasieupost.com/carlyss-drive-extension-redesigned-for-private-school-access-as-completion-moves-into-2027/
- Published: 2026-10-26T14:20:25.000Z
- Updated: 2026-10-26T14:20:25.000Z
- Author: The Calcasieu Post
- Tags: Local News

**CARLYSS, La. —** The Carlyss Drive Extension is undergoing design modifications to accommodate school traffic near Life Christian Academy, while its projected completion has shifted from summer 2026 to early 2027.

During an October Calcasieu Parish Police Jury meeting, Parish Engineer Nicholas Johnson confirmed that engineers modified the roadway to provide a dedicated turn lane into a school.

“We had to do some redesign on the fly,” Johnson told Police Juror Judd Bares.

**No Roundabout at Beglis Parkway**

Bares sought clarification about conflicting reports of a roundabout or five-lane intersection at Beglis Parkway.

Johnson confirmed the intersection will feature dedicated left- and right-turn lanes exiting Carlyss Drive and one incoming lane. No roundabout is planned.

The extension, connecting Wright Road to Beglis Parkway, was initially projected for completion in summer 2026 before the target moved to year’s end.

Johnson now anticipates construction wrapping up during the first quarter of 2027, possibly sooner.

**Additional Engineering Services Approved**

On October 1, the Police Jury approved an amendment to its professional engineering agreement with Aucoin & Associates, Inc., authorizing additional services for Phase 2.

The publicly available agenda does not identify the additional services or their cost.

It also does not establish whether the amendment was related to the school-access redesign.

The roadway improvements are intended to support transportation needs along the developing corridor, including access to nearby residential, commercial, and educational facilities.

**Construction Continues**

Johnson reported that crews were installing concrete curbing and gutters, preparing roadway base materials, and advancing work along the eastern portion of the extension.

The project also includes drainage improvements, water and sewer infrastructure, and pedestrian and bicycle accommodations.

**Construction is now projected to conclude between January and March 2027, with the completed extension providing a new connection between Wright Road and Beglis Parkway.**