# Inside the $846,000 Willow Street Deal: The Emails, the Money, and the FEMA Approval That Never Came
- URL: https://www.thecalcasieupost.com/inside-the-846-000-willow-street-deal-the-emails-the-money-and-the-fema-approval-that-never-came/
- Published: 2026-10-27T14:42:40.000Z
- Updated: 2026-10-28T14:34:30.000Z
- Author: The Calcasieu Post

**SULPHUR, La. —** On August 23, 2024, Finance Director Jennifer Thorn emailed the City Council with what sounded like a money-saving solution. 

A new temporary courthouse. A cheaper lease. And FEMA would reimburse the rent.

Councilwoman Joy Abshire replied:

**“why?? What are the merits for this particular building and what others did you look at??”**

Thorn responded with a list. The old Goodwill was too expensive to renovate. So was a building occupied by 10X Services. Other properties lacked space or required costly improvements.

The former Masonic Lodge at 501 Willow Avenue, she explained, met FEMA’s least-cost requirements. She projected 20% savings over the existing modular buildings. But one detail stood out.

**The future landlord didn’t own the building yet. He reportedly had it under contract.**

## **The $3 Million Warning**

Just 17 days later, two items appeared back-to-back on the September 9 council agenda.

**Item 5:** Introduce the Willow Avenue lease.

**Item 6:** Reduce budgeted FEMA reimbursement revenue by **$3 million** because the City had overestimated it.

The same administration proposing a new lease based partly on anticipated FEMA reimbursement was simultaneously acknowledging that it had overestimated federal reimbursements by $3 million in its previous budget.

Some residents have questioned why the council didn’t treat that shortfall as a warning to verify the new lease’s FEMA reimbursement eligibility before committing more taxpayer money.

## **Then Came the Money**

On October 1, council approved the lease. BAB Rentals LLC acquired the property shortly afterward for approximately $638,500\. Sulphur agreed to pay roughly $20,856 monthly. 

But taxpayers would also finance a parking lot on property the City didn’t own. Officials considered cheaper limestone designs before choosing concrete. The final concrete project wasn’t publicly bid.

The contractor received **$325,500**.

Its name?

**10X Services LLC.**

Its owner?

**Justin Babineaux.**

The same businessman whose other company collected the rent. City Court contributed $100,000 toward construction, but the total project exceeded Louisiana’s $250,000 public-works bidding threshold applicable at the time. Whether an exception applied remains unresolved.

## **Then Thorn Found the Check**

On January 9, 2026, Thorn questioned Babineaux’s reported parking contribution.

“I pulled the cleared check and we paid the total of $325,500.”

 Then came her acknowledgment,   **“This contradicts what I have been saying to folks.”**

 Babineaux reportedly funded other improvements, but the complete contribution remains unreconciled.

## **Remember That FEMA Reimbursement?**

Twelve days later, Thorn responded to journalist Natalie McLendon. The original FEMA project approved modular buildings. **501 Willow wasn’t included.**

More than a year after relocation, Thorn confirmed that no formal amendment requesting approval for Willow had been submitted. By October 2026, Mayor Jacob Stutes reported approximately $521,000 in rent payments.

## **FEMA reimbursement received: $0.**

Former Councilwoman Abshire says the appropriate application period hadn’t opened. Public Works Director Austin Abrahams says reimbursement may still be possible. Stutes believes procurement problems jeopardized it.

But requesting reimbursement and obtaining approval to change a federally funded project are different things.

## **What Taxpayers Were Actually Promised**

Sulphur needed temporary court facilities. That was never the issue. The issue is how a deal promising 20% savings and FEMA reimbursement has already cost taxpayers approximately **$846,500 in rent and parking improvements** on property the City doesn’t own.

**And the meter is still running.** If the new courthouse takes another two years to complete, staying at Willow Avenue could push that total to nearly **$1.35 million — more than twice what the landlord reportedly paid for the property.**

FEMA reimbursement remains uncertain, and the City still won’t own the building. 

**What was sold as a money-saving temporary solution could leave Sulphur taxpayers with a seven-figure bill and nothing permanent to show for their investment.**